JOB SUMMARY
​
Value
​
Duration
​
Location
​
​
£ 259,490
​
14 Weeks
​
Chelmsford
DESCRIPTION
​
Metro was the Principal Contractor for the demolition phase of this project and successfully completed full demolition of the site, including pre-demolition strip-out, asbestos removal, long reach demolition, lift slabs & foundations and crushed on site & stockpile for use during construction.
RESULTS
​
-
Zero Health, Safety & Environmental incidents
-
Minimal disruption to neighboring area
-
On Time
-
On Budget
-
97% Recycled
​